Temecula moves forward to relieve traffic congestion


Thursday, September 26th, 2013
Issue 39, Volume 17.
Tim O'Leary
Staff Writer


The recent purchases of several key parcels – deals totaling $4.5 million that will force several businesses to move or close – have set the stage for Temecula to build the city’s fifth bridge over Murrieta Creek.

The purchases – which will result in the city razing three buildings – are crucial pieces in traffic circulation project that will cost nearly $20 million when Overland Drive is eventually extended across Murrieta Creek.

The project, where work is expected to begin in February or March, would become the fourth major traffic circulation improvement to be under way at the same time in the fast-growing city.

"There’s a lot going on right now," said Greg Butler, Temecula’s longtime director of public works who was recently promoted to assistant city manager.

Two major projects – the replacement of the aging Main Street bridge and the first phase of the French Valley interchange – are now in full swing. The Overland Drive extension will now join another project – replacing the congested freeway interchange at Highway 79 South – in the on-deck circle.

In June, Temecula council members voted to spend $5.6 million to buy a final chunk of land – a site that includes a busy gas station, car wash and market – that will be needed to revamp the often-clogged exit and entrance ramps at Interstate 15 and Highway 79 South.

That purchase boosted the land acquisition costs to more than $13 million for the upcoming work aimed Advertisement
Advertisement for Christ the King  Lutheran Church
[ Christ the King Lutheran Church ]
at easing traffic congestion at that crucial traffic bottleneck. The cost of that project – including the construction work – will total about $45.3 million when the land, construction and other costs are totaled.

The construction work, which will cost nearly $14.5 million, is expected to begin before July and take a year or more to finish.

Within that time frame, work is also expected to begin on the extension of Overland Drive. That project will be done in two phases, and it will mark the end of another chapter in Temecula’s continuing efforts to connect the parts of the 30-square-mile city that are split by a flood-prone creek and an interstate highway.

The beginning of the Overland Drive saga began about 20 years ago, which was when many residents complained that bursts of new homes in the area were followed by snarled intersections and jammed freeway ramps.

City engineers expect to seek construction bids for the first phase of the project, which will extend Overland Drive to the creek’s eastern bank, in four to six months, Butler said. The construction portion of the first phase will cost more than $1.7 million and take about a year to complete.

The construction of the bridge, which will intersect with Diaz Road and Avenida Alvarado on the creek’s west side, will cost about $10 million. Depending on the availability of funds, that work is expected to start in the fiscal year that begins in July 2015, city documents show.


 

0 comments


arrow Be the first to share your opinion on this article!
 

Add your Comment


Name

Images, Formatting, or HTML is not allowed : plain text only. You may post up to 5 website addresses within your comment.




Disclaimer

The Fallbrook Village News has tightened its' policy regarding comments.
While we invite you to contribute your opinions and thoughts, we request that you refrain from using vulgar or obscene words and post only comments that directly pertain to the specific topic of the story or article.
Comments that are derogatory in nature have a high likelihood for editing or non-approval if they carry the possibility of being libelous.
The comment system is not intended as a forum for individuals or groups to air personal grievances against other individuals or groups.
Please, no advertising or trolling.
In posting a comment for consideration, users understand that their posts may be edited as necessary to meet system parameters, or the post may not be approved at all. By submitting a comment, you agree to all the rules and guidelines described here.
Most comments are approved or disregarded within one business day.

RSS FeedFacebookTwitter



Advertisement for Stellar Solar





Subscribe




Most Commented


Reach Local Customers



The Fallbrook Village News The Fallbrook Village News
760-723-7319 - 1588 S. Mission Rd. Suite 200, Fallbrook CA 92028
All contents copyright ©2014
About Us
Earthquake Information
Business Listings
Contact Us
Letter to the Editor
Report a website error
Sitemap
Online Digital Edition
RSS Feeds
Login