RMWD amends Hwy 76 realignment design


Thursday, February 14th, 2013
Issue 07, Volume 17.
Joe Naiman
Village News Correspondent


The Rainbow Municipal Water District approved a change order to its contract with Tetra Tech to design the realignment of district facilities in conjunction with the widening of State Route 76.

The district board voted 5-0 Jan. 22 to authorize the $116,000 change order. "Most of it had to do with actually preparing the construction plans," said Rainbow general manager Dave Seymour. "Now that Caltrans has decided where we can put them, we can direct Tetra Tech."

Tetra Tech and the Rainbow District have been working on the realignment design since January 2012. "That was a design for relocating district facilities," Seymour said.

"They’ll just be designing the new location," Seymour said. "The Caltrans contractor will actually do the work, but we have to do the design first."

The initial contract was for $69,200, and a previous amendment increased the budget to $115,709 which allowed Tetra Tech to address coordination issues.

Caltrans spent 2012 working on Advertisement
Advertisement for Casa Tiene Vista
[ Casa Tiene Vista ]
the design for the widening of Highway 76 between Sweetgrass Lane and Interstate 15, and the additional Caltrans information translated to additional work for Tetra Tech.

The additional tasks include preparation of legal descriptions and other documents for portions of the existing sewer line located within existing Caltrans easements which will be relinquished, rehabilitation of the existing sewer between Gird Road and Interstate 15, a review of a scour analysis and subsequent recommendations to protect the existing sewer at Live Oak Creek where Caltrans will replace the bridge, relocation of the sewer between Gird Road and I-15, additional meetings and site visits, additional design sheets and specifications, and updated conformance documents.

Seymour noted that some of the work would have been necessary without the highway project due to the age of the facilities. "Not all of it is related to the widening of the road, but most of it is," he said.


 

0 comments


arrow Be the first to share your opinion on this article!
 

Add your Comment


Name

Images, Formatting, or HTML is not allowed : plain text only. You may post up to 5 website addresses within your comment.




Disclaimer

The Fallbrook Village News has tightened its' policy regarding comments.
While we invite you to contribute your opinions and thoughts, we request that you refrain from using vulgar or obscene words and post only comments that directly pertain to the specific topic of the story or article.
Comments that are derogatory in nature have a high likelihood for editing or non-approval if they carry the possibility of being libelous.
The comment system is not intended as a forum for individuals or groups to air personal grievances against other individuals or groups.
Please, no advertising or trolling.
In posting a comment for consideration, users understand that their posts may be edited as necessary to meet system parameters, or the post may not be approved at all. By submitting a comment, you agree to all the rules and guidelines described here.
Most comments are approved or disregarded within one business day.

RSS FeedFacebookTwitter



Advertisement for Fallbrook Healthcare Partners


Subscribe





Most Commented


Reach Local Customers



The Fallbrook Village News The Fallbrook Village News
760-723-7319 - 1588 S. Mission Rd. Suite 200, Fallbrook CA 92028
All contents copyright ©2014
About Us
Earthquake Information
Business Listings
Contact Us
Letter to the Editor
Report a website error
Sitemap
Online Digital Edition
RSS Feeds
Login