Translate this page

FPUD awards sewer replacement design contract to KEH


FPUD GM also notes need for downtown village sewer rehab work


Thursday, January 10th, 2013
Issue 02, Volume 17.
Joe Naiman
Village News Correspondent


The Fallbrook Public Utility District awarded a contract to KEH and Associates to develop design documents and provide other design support for the eventual South Mission Phase II Sewer Replacement Project.

The 5-0 FPUD board vote Dec. 10 authorizes a contract for up to $55,000 with KEH for the design phase.

FPUD staff has completed an initial evaluation to determine how to replace some of the sewer mains within South Mission Road which are above or near capacity. If a sewer section is at or near capacity, it is not in compliance with current sewer design standards and thus at risk for overflows and subsequent Regional Water Quality Control Board fines.

"This is one of several that were going to be doing over the next several years," said FPUD general manager Brian Brady.

"There are several Downtown Village sewer systems or segments that are old," Brady said. "They need to be rehabbed and theyre pretty hard to get at."

Brady explained that the age of the system segments along with the area around them having been built up makes those segments harder to access.

"The Downtown Village area is, of course, critical, and it is the oldest part of the system so Advertisement
Advertisement for Christ the King  Lutheran Church
[ Christ the King Lutheran Church ]
its a high priority for us," Brady said.

FPUD divided the project into several phases in order to keep within district budget constraints. The first phase was open trench construction which did not have major traffic impacts, and FPUD staff was able to complete the design and construction of that phase. The next phase will likely require trenchless construction due to issues including creek and storm drain crossings, traffic mitigation, and access. FPUDs staff does not have experience in design or construction for trenchless construction projects and recommended to the FPUD board that the design be completed by a consultant.

FPUD prepared a request for proposals to design the replacement of the South Mission Phase II sewer system and received responses from three firms. FPUD staff conducted an evaluation of the proposals based on overall approach, experience, cost, and schedule while interviewing representatives of the firms. The process determined that KEH and Associates was the most qualified of the three firms. KEH also submitted the lowest bid.

The design phase is expected to be completed by Spring 2013, and construction will likely begin during Fiscal Year 2013-14. The actual replacement project will cost approximately half a million dollars.


 

0 comments


arrow Be the first to share your opinion on this article!
 

Add your Comment


Name

Images, Formatting, or HTML is not allowed : plain text only. You may post up to 5 website addresses within your comment.




Disclaimer

The Fallbrook Village News has tightened its' policy regarding comments.
While we invite you to contribute your opinions and thoughts, we request that you refrain from using vulgar or obscene words and post only comments that directly pertain to the specific topic of the story or article.
Comments that are derogatory in nature have a high likelihood for editing or non-approval if they carry the possibility of being libelous.
The comment system is not intended as a forum for individuals or groups to air personal grievances against other individuals or groups.
Please, no advertising or trolling.
In posting a comment for consideration, users understand that their posts may be edited as necessary to meet system parameters, or the post may not be approved at all. By submitting a comment, you agree to all the rules and guidelines described here.
Most comments are approved or disregarded within one business day.

RSS FeedFacebookTwitter



Advertisement for Fallbrook Healthcare Partners





Subscribe




Most Commented


Reach Local Customers



The Fallbrook Village News The Fallbrook Village News
760-723-7319 - 1588 S. Mission Rd. Suite 200, Fallbrook CA 92028
All contents copyright ©2014
About Us
Earthquake Information
Business Listings
Contact Us
Letter to the Editor
Report a website error
Sitemap
Online Digital Edition
RSS Feeds
Login